SignalsAZ.com Prescott News Podcast - Glassford Hill Road Widening Project Update | Jun 8th - 12th, 2026

Episode Date: June 8, 2026

Send us a text and chime in!Final Round of Asphalt Paving to Begin in First Phase Crews will be performing the final round of asphalt paving within the first phase of work along Glassford Hill Road, f...rom just north of Long Look Drive to just south of Spouse Drive. Following the completion of paving operations, roadway striping will occur. Please be aware of the following impacts: Monday, June 8 through Friday, June 12, 7 a.m. – 7 p.m., One lane of traffic in each direction of Glassford Hill Road will always remain open throughout construction. Businesses, schools and residential communities will remain fully accessible throughout the...   For the written story, read here >> https://www.signalsaz.com/articles/glassford-hill-road-widening-project-update-jun-8th-12th-2026/ Check out the CAST11.com Website at: https://CAST11.com Follow the CAST11 Podcast Network on Facebook at: https://Facebook.com/CAST11AZFollow Cast11 Instagram at: https://www.instagram.com/cast11_podcast_network

Transcript
Discussion (0)
Starting point is 00:00:00 Text to Speech Audio articles made possible on the Cast11.com podcast network by Fane Signature Group. Final round of asphalt paving to begin in first phase. Cruise will be performing the final round of asphalt paving within the first phase of work along Glassford Hill Road, from just north of Long Look Drive to just south of Spouse Drive. Following the completion of paving operations, roadway striping will occur. Please be aware of the following impacts. Monday, June 8th through Friday, June 12th, 7 a.m. to 7 p.m. One lane of traffic in each direction of Glassford Hill Road will always remain open throughout construction. Businesses, schools and
Starting point is 00:00:40 residential communities will remain fully accessible throughout the project. Motorists can expect travel delays, construction equipment in the roadway and traffic control devices. Periodic sidewalk and pedestrian closures may be necessary. Please follow the March signage, drive safely throughout the project corridor and consider using an alternative route if possible. Construction activities ongoing along Glassford Hill Road. Cruise will continue the following work along Glassford Hill Road, between Bear Path and Santa Fe Loop Road. Curb, gutter and sidewalk placement. Drainage pipes, structures and culvert installation. Retaining wall construction. Please be aware of the following impacts. Monday, June 8th through Friday, June 12th, 7 a.m. to 7 p.m. One lane of traffic in each direction of
Starting point is 00:01:28 Glassford Hill Road will always remain open throughout construction. Businesses, schools and residential communities will remain fully accessible throughout the project. Motorists can expect travel delays, construction equipment in the roadway and traffic control devices. Periodic sidewalk and pedestrian closures may be necessary. Please follow the March signage, drive safely throughout the project corridor and consider using an alternative route if possible. Catch up with more local news stories on signalsaz.com. Subscribe and be the F1 RST2 No.

There aren't comments yet for this episode. Click on any sentence in the transcript to leave a comment.